Plastic

Silo Project

Polycarbonate resin storage silo, with multiple vacuum and pressure powder transfer systems and a truck loading system.

Capital Costs: $4,000,000

New Extrusion Line

Provided the “preliminary” and “detailed” engineering services for the installation of a new 70mm extruder line to replace an old Baker-Perkins right angle unit. Work included Civil-Structural-Instrumentation-Electrical-Mechanical to install all new feeders, dust collectors, extruder, receiving vessels, water bath, pelletizer and associated piping. Demolition of the old unit and associated equipment was also involved.

Capital Costs: $4,800,000

PEP and Extruder Installations

Prepared a preliminary engineering estimate package (PEP) and a +20% estimate for three new extruder lines, a new building extension, a power upgrade, packaging and raw material delivery system upgrades and site services upgrades.  PEP package for AR generation purposes and receiving engineering bids for the detailed design phase of the project.

Capital Costs: $10,000,000