Utilities

Boilerhouse

Layout, design and oversee construction for 5,300 square foot boilerhouse expansion for the installation of a 206,000 lbs./hr., gas-fired B & W steam boiler.

Capital Costs: $11,600,000

Piping System

Installation of a piping system and tank to supply softened water.

Capital Costs: $150,000

Air Separation Unit

Completed electrical design for the installation of an ASU (Air Separation Unit) from the incoming power supply to the individual end users. Plot plans were redone on scale suitable for power and instrumentation drawings. Cable tray layouts were done for all instrumentation, control and 480V power cables. Conduit and cable schedules for all plant cables, including cooling tower and control building. Elementary and schematic diagrams were done for all motors, lube oil pumps and lube oil heaters. Preparation of contractor ...